EDAC Engineering commissions 660 MW at NTPC’s Tanda Thermal Power Plant
4th Dec 2019

EDAC Engineering has successfully commissioned 660 MW at NTPC’s Tanda Thermal Power Plant (TTPP). EDAC Engineering had been contracted by GE Power for the Erection, Testing and commissioning of Two Units (Unit - 5 & 6) of turbine & generator and its Auxiliaries at 2 x 660 MW of NTPC Tanda Thermal Power Projects.

The unit commissioned was the first phase of EDAC's contract and the fifth unit of NTPC in the Tanda project. Following the commissioning, the installed capacity of NTPC's Tanda plant has been increased from 440 MW to 1100 MW. The full load of the unit will lead to a significant increase in power generation at Uttar Pradesh.

NTPC is the largest power utility company in India and has presence in Coal, Gas, Solar PV, Hydro and Wind Power Generation and Coal Mining.